PROJECT TIMELINE

 

Fall 2018 Project Development
Ongoing Stakeholder Outreach
March 19, 2019  Open House 
March 29, 2019  Filed FERC Application 
April 12, 2019 FERC Issued Notice of Application
May 3, 2019 Formal Comment Period Ends
May 13, 2019
FERC Issues Notice of Intent to Prepare Environmental Assessment
June 12, 2019
Scoping Comments for the Environmental Assessment are due
June 3, 2019
FERC Issues Notice of Schedule for Environmental Review
2Q 2020* Anticipate Receiving FERC Order
2Q 2020* Begin Construction
4Q 2020* Target In-Service

 

 

Items shown in red font reflect the latest updates.

*Subject to regulatory approval.