PROJECT TIMELINE

 

October 9, 2018 

Filed Application with FERC    

October 19, 2018

FERC issue Notice of Application

 

November 9, 2018 

 

Formal public comment period ends 
November 20, 2018 FERC issues Notice of Intent to Prepare Environmental Assessment 

December 20, 2018

Scoping Comments for the Environmental Assessment were due
June 2019 Forecasted Receipt of FERC Certificate (Project Approval)
3rd Quarter 2019 Anticipated Construction Start

June 2020

Target In-Service Date

 

 

Items shown in red font reflect the latest updates.

*Subject to customary approval.