PROJECT TIMELINE

 

October 9, 2018

Filed Application with FERC    

October 19, 2018

 

FERC issue Notice of Application

 

November 9, 2018 

 
 
Formal public comment period ends 
November 20, 2018 FERC issues Notice of Intent to Prepare Environmental Assessment 

December 20, 2018

Scoping Comments for the Environmental Assessment were due

January 10, 2019

FERC Issues Notice of Schedule for Environmental Review of the Petal III Compression Project

 

April 3, 2019

 

 

FERC Issues Environmental Assessment

 

May 3, 2019    

 

Comments on Environmental Assessment were due at FERC
June 2019 Forecasted Receipt of FERC Certificate (Project Approval)
3rd Quarter 2019 Anticipated Construction Start

June 2020

Target In-Service Date

 

 

Items shown in red font reflect the latest updates.

*Subject to customary approval.