PROJECT TIMELINE

 

 

Fall 2017 Project Development Activities
   
February 2018 State / County Outreach
   
May 14, 2018  Community Open House in Goodrich, TX at First Baptist Church 
   
June 7, 2018 Community Open House in Willis, TX at North Montgomery Community Center
   
July 13, 2018 

Filed Application with FERC 

   
July 26, 2018 FERC issues Notice of Application
   
August 16, 2018 Formal comments to FERC ended (affected landowners may continue to comment)
   
August 31, 2018 FERC issued the Notice of Intent to Prepare an Environmental Assessment
     
October 1, 2018 Scoping Comments for the Environmental Assessment were due at FERC
   
November 19, 2018 FERC Issues Notice of Schedule for Environmental Review of the Willis Lateral Project
   
March 4, 2019
Anticipated receipt date of FERC Environmental Assessment
   
3rd Quarter 2019* Forecasted Receipt of FERC Certificate (Project Approval)
   
4th Quarter 2019* Anticipated Construction Start
   
Mid-2020* Target In-Service Date
   
   
   
   
   

 

Items shown in red font reflect the latest updates.

*Subject to customary approval.