PROJECT TIMELINE

 

Spring 2017 Project Development Activities
   
June - Sept. 2017     State / Parish / Local Outreach
   
July 20, 2017       Filed Application with FERC 
   
July 31, 2017

FERC issued Notice of Application

   
August 21, 2017  Formal comments to FERC ended (affected landowners may continue to submit comments)
   
August 24, 2017  Community Open House at Westlake City Hall  
   
August 30, 2017  FERC issued the Notice of Intent to Prepare an Environmental Assessment 
   
September 29, 2017       Scoping Comments for the Environmental Assessment were due at FERC   
   
November 17, 2017 Received State Air Permit from the Louisiana Dept. of Environmental Quality 
   
December 14, 2017 FERC issued the Notice of Schedule for issuing the Environmental Assessment 
   
4th Quarter 2017 On-going local outreach
   
February 27, 2018 FERC issued the Environmental Assessment
   
March 27, 2018  Comments for the Environmental Assessment were due at FERC  
   
May 17, 2018  FERC issued Certificate Approving Project 
   
October 1, 2018   FERC issued approval to commence construction
   
October 31, 2018 Construction commenced
   
3rd Quarter 2019* Target In-Service Date
   

 

Items shown in red font reflect the latest updates.

 *Subject to customary approval.