Project Timeline

 

March - June 2016             Project Development Activities
   
July 11, 2016 Filed Application with FERC
   
March 3, 2017  FERC issued the Environmental Assessment  
   
October 6, 2017    FERC issued Certificate Approving Project
   
January 9, 2018  FERC issued approval to commence construction 
   
February 5, 2018  Construction Activities Commenced
   
May 29, 2018 Update meeting with Parish
   
October 9, 2018 Filed In-Service Request with FERC
     
October 30, 2018     Follow-up meeting with Mayor of Westlake
   
October 31, 2018   FERC issued in-service approval 
   
November 1, 2018 Montz Compressor Station placed in-service

 

Items shown in red font reflect the latest updates.

*Subject to customary approval.