Project Timeline

 

October 30, 2014

Submitted NEPA Pre-filing Request with FERC
   
November 5, 2014 FERC accepts Gulf South into Pre-filing Process
   
January/February 2015  Open Houses and Informational Meetings were Conducted
   
June 12, 2015 Filed Certificate Application
   
January 29, 2016 FERC Issued the Environmental Assessment
   
June 20, 2016     FERC Granted Approval  
   
December 5, 2016  Construction Commenced at Wilson Compressor Station  
   
February 6, 2017  Commenced Preparing Pipeline Right-of-Way for Construction
   
February 22, 2017  Filed Amendment Application for Magasco Compressor Station
   
March 20, 2017   Commenced Brazos Compressor Station - Initial Construction 
   
April 2017 Commenced Pipeline Construction 
   
May 24, 2017 FERC Granted Approval for Magasco Amendment
   
July 10, 2017   Commenced Goodrich Compressor Station Piping Modifications
   
July 18, 2017  Commenced Brazos Compressor Station Construction
   
August 17, 2017   Commenced North Houston Compressor Station - Initial Construction
   
January 9, 2018  Filed Request for Authorization to Place Certain Facilities In-Service 
   
January 31, 2018  FERC approves request to Place Certain Facilities In-Service 
   
February 1, 2018 Placed Certain Facilities In-Service 
   
February 19, 2018 Commenced Magasco Compressor Station Construction
   
March 13, 2018 Commenced North Houston Compressor Station Construction
   
April 2, 2018 Transco Meter and Regulator Station placed In-Service 
   
May 11, 2018 Filed Extension Request for the North Houston and Wilson Compressor Stations
   
May 18, 2018 FERC approves Extension Request for the North Houston and Wilson Compressor Stations
   
May 18, 2018 Filed supplemental request to place the Brazos Compressor Station in-service
   
June 1, 2018 Placed Brazos Compressor Station In-Service
   
October 9, 2018 Filed request to place the Magasco, North Houston, and Wilson Compressor Stations in-service with the FERC
    
October 30, 2018 FERC approves request to place the Magasco, North Houston, and Wilson Compressor Stations in-service  
   
November 1, 2018 Gulf South made available and placed in-service the Wilson Compressor Station.
   
November 14, 2018
Gulf South made available and placed in-service the Magasco Compressor Station. 
   
December 31, 2018
Guf South made available and placed in-service the North Houston Compressor Station.

 

Items shown in red font reflect the latest updates.